Home · Everyday · Life, School & Work · PERT Calculator
PERT Calculator
Combines optimistic, most-likely and pessimistic estimates into the PERT expected duration, standard deviation and variance.
What this calculator does
Combines optimistic, most-likely and pessimistic estimates into the PERT expected duration, standard deviation and variance. Where a measure is involved, US and metric units are both accepted — flip the unit toggle and the figures convert with the same definitions the formula uses. Every result on this page is computed from the formula stated below, with no hidden rounding steps.
The formula and method
PERT weights the most likely estimate four times the optimistic and pessimistic ones: expected duration tₑ = (O + 4M + P)/6. The standard deviation is approximated as (P − O)/6, treating the spread between extremes as roughly six sigma, and the variance is its square.
The formulas assume activity durations follow a beta distribution and that estimates are honest extremes, not padded or sandbagged. For a project path, expected durations add, and variances add (for independent activities) — standard deviations do not.
Worked example
With the example inputs this page opens with (optimistic estimate 4, most likely estimate 8, pessimistic estimate 16), the result is 8.667 — expected duration. Computed from the inputs on this page with the formula below — change any figure and every result updates.
Quick reference
| Pessimistic estimate | Expected duration | Standard deviation | Variance |
|---|---|---|---|
| 10 | 7.666667 | 1 | 1 |
| 12 | 8 | 1.333333 | 1.777778 |
| 16 | 8.666667 | 2 | 4 |
| 20 | 9.333333 | 2.666667 | 7.111111 |
| 24 | 10 | 3.333333 | 11.111111 |
| 30 | 11 | 4.333333 | 18.777778 |
Computed with the same formulas as the calculator above — enter any values there for figures beyond this table.
Common questions
Why is the most likely estimate weighted 4×?
The weighting approximates the mean of the beta distribution PERT assumes for task durations, pulling the expected value toward the mode without ignoring the tails.
How does the PERT Calculator work?
Combines optimistic, most-likely and pessimistic estimates into the PERT expected duration, standard deviation and variance. Optimistic · Most likely · Pessimistic → Expected duration. The result updates as you type, and the formula and method on this page state the exact definitions used, so you can reproduce the calculation by hand.
What inputs does the PERT Calculator need?
Optimistic · Most likely · Pessimistic → Expected duration. Invalid entries — such as a zero denominator, an out-of-range value or a malformed list — produce a plain-language message instead of a misleading number.
Is the PERT Calculator free to use?
Yes. It runs entirely in your browser with no sign-up, and the same calculator is available as an embeddable widget via the Embed button, so it can be placed on another site with its calculation intact.