Slack Time Calculator

Find an activity's total float in a project schedule: how far its start can slip, from the earliest and latest start and finish dates.

Your figures

Example result — edit the figures to make it yours

4 days

Total float (slack)

Float from finish dates3.0 days
Activity duration9.0 days

What this calculator does

Find an activity's total float in a project schedule: how far its start can slip, from the earliest and latest start and finish dates. Where a measure is involved, US and metric units are both accepted — flip the unit toggle and the figures convert with the same definitions the formula uses. Every result on this page is computed from the formula stated below, with no hidden rounding steps.

The formula and method

Slack (total float) = late start − early start, cross-checked against late finish − early finish

All four dates use the same day numbering from the project start. On a correctly built network the start-based and finish-based floats agree; a mismatch signals an inconsistency in the schedule.

Zero slack marks a critical activity: any delay to it delays the whole project. The activity duration shown is early finish − early start.

Worked example

With the example inputs this page opens with (late start (day) 12, early start (day) 8, late finish (day) 20, early finish (day) 17), the result is 4.0 days — total float (slack).

Quick reference

Quick reference — varying late start (day)
Late start (day)Total float (slack)
6-2.0 days
9.61.6 days
124.0 days
157.0 days
1810.0 days
2416.0 days

Computed with the same formulas as the calculator above — enter any values there for figures beyond this table.

Common questions

What does zero slack mean?

The activity is on the critical path: it cannot start or finish late by any amount without pushing back the project's end date.

Why show float from both start and finish dates?

In a consistent network the two are equal, so showing both is a built-in sanity check on the earliest and latest dates you entered.

How does the Slack Time Calculator work?

Find an activity's total float in a project schedule: how far its start can slip, from the earliest and latest start and finish dates. Late start · Early start · Late finish · Early finish → Slack in days. The result updates as you type, and the formula and method on this page state the exact definitions used, so you can reproduce the calculation by hand.

What inputs does the Slack Time Calculator need?

Late start · Early start · Late finish · Early finish → Slack in days. Invalid entries — such as a zero denominator, an out-of-range value or a malformed list — produce a plain-language message instead of a misleading number.