What this calculator is for
Patios, walkways and paved pads laid with individual pavers on a gravel-and-sand build-up. It counts the pavers themselves and the three materials around them: base gravel underneath, bedding sand the pavers sit on, and joint sand swept between them. If your area is not a rectangle, split it into rectangles, calculate each, and add the counts.
Formula and assumptions
Each paver is modelled as covering its face plus one joint width on every side, so the count follows the joint you enter — a planning assumption, not an engineering standard; use the joint your paver system and pattern call for. Base gravel and bedding sand are simple layer volumes (area × depth ÷ 324 gives cubic yards) at the depths you enter, with the same allowance applied. Joint sand fills only the joint fraction of the paver layer, using the paver thickness you enter, and carries no allowance. The count assumes a rectangular area in a running pattern with no cuts modelled individually — the allowance covers cuts, breakage and spares. Base preparation, edge restraints and compaction follow your local conditions and supplier guidance; this page makes no structural claims about the build-up.
Reading your result
The big figure is the number of pavers to buy, allowance included and rounded up — you cannot buy part of a paver. Under it, the exact count before the allowance, so you can see what the allowance added. Base gravel and bedding sand are the layer volumes to order at your chosen depths; joint sand is the smaller volume swept in after laying, shown in cubic feet (or litres in Metric). If a supplier sells pavers by the pallet or by coverage area, compare their stated coverage against the area shown here before converting the count.
Worked example
A 16 ft × 12 ft patio (192 sq ft) with 8 in × 4 in pavers and a ⅛ in joint: each paver covers 33.52 sq in including its joint, so the exact count is ≈ 825 pavers; with a 10% allowance that becomes 908 pavers to buy. Underneath: 2.61 yd³ of base gravel at 4 in deep and 0.65 yd³ of bedding sand at 1 in deep, plus 1.72 ft³ of joint sand. These figures are computed by the same tested function the calculator above runs — change the inputs and they move together.
Common mistakes
Counting pavers by face area alone. Dividing the area by the paver's face size ignores the joints and overstates coverage — the wider the joint, the bigger the error. Ordering base and bedding to the same depth. They are different layers with different jobs; enter each depth separately. Forgetting edge cuts. Unless your area is an exact multiple of the paver-plus-joint module, the perimeter is all cuts — that is what the allowance is for, and patterned layouts need more of it. Measuring inside the edging. Measure the full area the pavers will cover, including under the edge restraints. Treating the default depths as a specification. They are planning starting points; your soil and drainage decide the real build-up.
Quick reference: common areas
Pavers to buy and base gravel for common areas, using the calculator's default 8 in × 4 in paver, ⅛ in joint, 4 in base and 10% allowance, computed by the same function:
| Project | Length | Width | Pavers to buy | Base gravel |
|---|---|---|---|---|
| Walkway | 12 ft | 3 ft | 171 | 0.49 yd³ |
| Small patio | 12 ft | 12 ft | 681 | 1.96 yd³ |
| Patio | 16 ft | 12 ft | 908 | 2.61 yd³ |
| Large patio | 20 ft | 16 ft | 1,513 | 4.35 yd³ |
| Courtyard | 20 ft | 20 ft | 1,891 | 5.43 yd³ |
Different paver size, joint or depths? Run the calculator above — the table only mirrors its defaults.
Common questions
How deep should the base gravel and bedding sand be?
This calculator does not set those depths for you — they are editable planning assumptions, not engineering standards. The defaults (4 in of base gravel, 1 in of bedding sand) are common planning starting points; soil, drainage and local practice decide the real build-up. Change the depths and the gravel and sand volumes follow; the paver count does not depend on them.
Why does the paver count use a joint width?
Pavers are not laid touching: each paver effectively occupies its own face plus the joint around it. The model gives every paver a footprint of (length + joint) × (width + joint), so a wider joint means fewer pavers cover the same area — and the gap fraction is exactly what the joint-sand volume fills. Set the joint to 0 to model a tight-laid pattern.
Does the pattern I choose change the count?
The count assumes a simple rectangular area in a running pattern, with no cuts modelled individually — the allowance is what covers cuts, breakage and spares. Intricate patterns (herringbone, baskets, borders in a second size) cut more pieces at the edges, so raise the allowance rather than expecting the base count to absorb it.
What is joint sand, and why is it separate from bedding sand?
Bedding sand is the layer the pavers sit on, under the paver layer. Joint sand is swept into the gaps between pavers after laying, so it is sized from the joint fraction of the paver layer's thickness — a different volume, worked out separately here. Joint sand carries no allowance in this model; bedding and base volumes do.