What this calculator is for
Driveways, parking pads and private lanes: how many cubic yards of asphalt a rectangular area at a given compacted thickness contains, and what that volume weighs in tons at a stated density — the two figures an asphalt plant will quote and dispatch against.
Formula and assumptions
The volume half is exact geometry — the same 324 divisor as any inch-depth volume. The tonnage half rests on one clearly labelled assumption: the density you enter, pre-filled at 145 lb/ft³ as a common planning figure for compacted asphalt. It is an assumption, not a property this page guarantees: your mix's real density comes from your plant, and swapping their figure into the density field updates the tonnage while the volume stays fixed. The thickness is the compacted, finished thickness. No waste, overlap or edge allowance is included.
Reading your result
The big figure is the tonnage to order at your density. The volume in cubic yards is density-independent — use it to cross-check a quote given by volume. If a quote's tonnage differs from yours, the first thing to compare is the density each side assumed, then the thickness: half an inch of thickness on a large driveway moves the tonnage more than any rounding does.
Worked example
A 10 ft × 10 ft pad at 4 in compacted: volume = 10 × 10 × 4 ÷ 324 ≈ 1.23 yd³. At the stated density assumption of 145 lb/ft³, that is 4,833.333 lb ≈ 2.42 short tons. These figures are computed by the same tested function the calculator above runs — change the inputs, including the density, and they move together.
Common mistakes
Entering the loose-lay thickness instead of the compacted thickness, which overstates the volume. Comparing quotes without comparing densities — two plants can quote honestly different tonnages for the same driveway if their assumed densities differ. Measuring only the paved rectangle and forgetting aprons and flared ends; add those areas as their own rectangles. Ordering to the exact tonnage with no allowance for edges and joints.
Quick reference: common driveways at 4 in compacted
Volumes and tonnages at the stated 145 lb/ft³ density assumption, computed by the same function as the calculator:
| Driveway | Length | Width | Volume | Tonnage |
|---|---|---|---|---|
| Small pad | 10 ft | 10 ft | 1.23 yd³ | 2.42 tons |
| 1-car driveway | 20 ft | 10 ft | 2.47 yd³ | 4.83 tons |
| 2-car driveway | 20 ft | 20 ft | 4.94 yd³ | 9.67 tons |
| Long driveway | 50 ft | 12 ft | 7.41 yd³ | 14.50 tons |
| Parking area | 30 ft | 30 ft | 11.11 yd³ | 21.75 tons |
Tonnage follows the 145 lb/ft³ assumption — your plant's density figure may differ.
Common questions
Why is the density an input instead of a fixed number?
Because tonnage is volume × density, and compacted asphalt density varies with the mix design and aggregate. 145 lb/ft³ is a common planning figure, so it is pre-filled — but it is labelled as an assumption everywhere it is used, and you can replace it with your plant's figure for your mix. The volume in cubic yards does not depend on density at all; only the tonnage does.
Should the thickness be the loose or compacted depth?
Compacted — the finished thickness after rolling. That is the volume that ends up on the ground, and it is what this calculator multiplies. If your contractor quotes a loose-lay depth, the compacted figure will be smaller; ask which one their number refers to before entering it.
Is any waste or overlap allowance included?
No. The result is the exact geometric volume of a rectangle at one uniform thickness. Real jobs lose material to edges, joints, trucking and thickness variation, so add your own allowance on top — your paving contractor will have a view on how much for your site.
My driveway is not a rectangle — what do I do?
Split it into rectangles (and triangles where it tapers), calculate each piece, and add the volumes. For a triangle use half the base × height as its area, then treat it as a rectangle of that area at the same thickness. Curves can be approximated with several short rectangles.